Maxim work with a large number of air conditioning companies to assist with the lifting and positioning of equipment. Here you can see one of the Maxim teams working at Royal Leamington Spa hospital, our client wanted to avoid crane lifting as the only way to access the installation would be over a live building. Maxim conducted site surveys and meetings and produced a plan to lift and shift the equipment from transport to the final location using a varied selection of equipment including porta gantries, skates, jacks.
Due to the building being a live hospital our client requested we cause minimal disruption and kept noise levels to a minimum, this was all considered on drawing up the plans and made for a very happy client on completion.